Question: How could the manager use this information? Problem 3 : An Assembly Line Balancing Problem A Shop works a 4 0 0 - minute day.

How could the manager use this information?
Problem 3: An Assembly Line Balancing Problem
A Shop works a 400-minute day. The manager of the shop wants an output of 200 units per day
for the assembly line that has the elemental tasks shown in the table.
Please:
Construct the precedence diagram.
Assign tasks using the most-following-tasks rule as the primary rule and the greatest-
positional-weight rule as the secondary rule.
Compute the balance delay and the efficiency of your balance.
Problem 4: Project Management and Quantity Discount Inventory Problems
Problem 4A: A Small Project Management Problem
You are working on a project that has 12 activities and you want to perform a PERT analysis on
the project. You determine that the critical path consists of only five activities. You then
compute the variances for the five critical activities and these variances are 3,4,2,1, and 6 days
If the desired completion date for the project is 50 days, and the expected completion date for it
(the project) is 40 days, what is the probability that the project completion time will not be more
than the desired completion date?
 How could the manager use this information? Problem 3: An Assembly

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!