Question: Problem 3 : An Assembly Line Balancing Problem A Shop works a 4 0 0 - minute day. The manager of the shop wants an

Problem 3: An Assembly Line Balancing Problem
A Shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table.
Task. Immediate successor. Task-time.
a b, c, d 0.5
b e 1.4
c e 1.2
d f 0.7
e g, j 0.5
f i 1.0
g h 0.4
h k 0.3
i j 0.5
j k 0.8
k m 0.9
m end. 0.3
Please:
1. Construct the precedence diagram.
2. Assign tasks using the most-following-tasks rule as the primary rule and the greatest-positional-weight rule as the secondary rule.
3. Compute the balance delay and the efficiency of your balance.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!