Question: how did they get that answer? A MRP primary report is in the table. Lead time is 3 weeks. Use fixed lot size of 1000

how did they get that answer? how did they get that answer? A MRP primary
A MRP primary report is in the table. Lead time is 3 weeks. Use fixed lot size of 1000 units (POR can be a multiple of 1000 units). No backorder allowed. What should be POR for week 1? Please fill in just an integer number. Week GR 1 300 1700 3,588 600 850 1000 1000 3000 PA POR Answer: 3,000