Activity | Duration | ES | EF | LS | LF | SLACK | CRITICAL |
A | 27 | 0 | 27 | 0 | 27 | ||
B | 55 | 27 | 82 | ||||
C | 65 | 27 | 92 | ||||
D | 56 | 92 | 148 | ||||
E | 40 | 82 | 122 | ||||
F | 1.5 | 122 | 123.5 | ||||
G | 26 | 148 | 174 | ||||
H | 25 | 174 | 199 | ||||
I | 30 | 199 | 229 | ||||
J | 10 | 199 | 209 | ||||
K | 1 | 209 | 210 | ||||
L | 30 | 229 | 259 | ||||