Question: How do I get EV and PV if the estimated cost is $81K? In $000 % Complete EV AC PV CV SV Status Report: Ending

How do I get EV and PV if the estimated cost is $81K?How do I get EV and PV if the estimated cost is

In $000 % Complete EV AC PV CV SV Status Report: Ending Period 1 Tasks A 50% 2 4 2 -2 0 B 40% 10 8 10 2 0 C 25% 5 3 10 2 -5 17 15 22 2 -5 Cumulative Totals Status Report: Ending Period 2 Tasks Finished A 4 8 4 -4 0 80% B 20 14 20 6 0 75% 15 8 20 7 -5 Cumulative Totals 39 30 44 9 -5 Status Report: Ending Period 3 Tasks A Finished 8 4 80% B 15 25 Finished 10 20 D D 50% 4 3 IIIIDUD 0% E 0 0 33.3% (1/3) F 4 3 Cumulative Totals 41 55 Status Report: Ending Period 4 Tasks Finished A 8 B Finished 16 Finished 10 Finished D 8 E E 33.3% (1/3) 3 F F 66.7% (2/3) 8 8 Cumulative Totals 53 In $000 % Complete EV AC PV CV SV Status Report: Ending Period 1 Tasks A 50% 2 4 2 -2 0 B 40% 10 8 10 2 0 C 25% 5 3 10 2 -5 17 15 22 2 -5 Cumulative Totals Status Report: Ending Period 2 Tasks Finished A 4 8 4 -4 0 80% B 20 14 20 6 0 75% 15 8 20 7 -5 Cumulative Totals 39 30 44 9 -5 Status Report: Ending Period 3 Tasks A Finished 8 4 80% B 15 25 Finished 10 20 D D 50% 4 3 IIIIDUD 0% E 0 0 33.3% (1/3) F 4 3 Cumulative Totals 41 55 Status Report: Ending Period 4 Tasks Finished A 8 B Finished 16 Finished 10 Finished D 8 E E 33.3% (1/3) 3 F F 66.7% (2/3) 8 8 Cumulative Totals 53

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!