Question: How do you access a calendar for your project so you can review working and nonworking days? A Use a calendar template. B Double -

How do you access a calendar for your project so you can review working and nonworking days?
A
Use a calendar template.
B
Double-click a start date in the Gantt Chart.
C
Use the Project Information dialog box.
D
Use the Change Working Time dialog box.