Question: How do you find the slack days (Part C)? Can you show step by step how to get it done because I am extremely confused.


How do you find the slack days (Part C)? Can you show step by step how to get it done because I am extremely confused. Please make it legible.
Start Star OC. Start 6 Finish Start Elnlsh b. Determine the critical path and project duration The critical path is path A-C-E and the project duration is 16 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Activity Slack (days OOO Paul Silver, owner of Sculptures Intemational, just initiated a new art project. The following data are available for the project: Activity Activity Time (days) Immediate Predecessor(s) a. Choose the correct network diagram for the project. . Start. Finish Start on m Finish o CD) A - Finish o b. Determine the critical path and project durationStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock