Question: How do you find the slack days (Part C)? Can you show step by step how to get it done because I am extremely confused.

How do you find the slack days (Part C)? Can youHow do you find the slack days (Part C)? Can you

How do you find the slack days (Part C)? Can you show step by step how to get it done because I am extremely confused. Please make it legible.

Start Star OC. Start 6 Finish Start Elnlsh b. Determine the critical path and project duration The critical path is path A-C-E and the project duration is 16 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Activity Slack (days OOO Paul Silver, owner of Sculptures Intemational, just initiated a new art project. The following data are available for the project: Activity Activity Time (days) Immediate Predecessor(s) a. Choose the correct network diagram for the project. . Start. Finish Start on m Finish o CD) A - Finish o b. Determine the critical path and project duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!