Question: How does a net requirement differ from a gross requirement in MRP ? A ) Net requirement includes scheduled receipts and on - hand inventory,
How does a "net requirement" differ from a "gross requirement" in MRP
A Net requirement includes scheduled receipts and onhand inventory, while gross requirement does not.
B Gross requirement includes scheduled receipts and onhand inventory, while net requirement does not.
C Both are the same in MRP
D Net requirement is always greater than gross requirement.