Question: How does the project manager handle change requests in organisations without a Change Control Board ( CCB ) ? Group of answer choices A )

How does the project manager handle change requests in organisations without a Change Control Board (CCB)?
Group of answer choices
A) By documenting and managing changes independently
B) By ignoring change requests until a CCB is established
C) By delegating change management to the team members
D) By immediately implementing all change requests