Question: How is Planned Value calculated? How is Planned Value calculated? The cumulative price of billable work that was planned to be installed up to a
How is Planned Value calculated? How is Planned Value calculated? The cumulative price of billable work that was planned to be installed up to a given point in time The number of work days originally planned up to a point in time Contract price divided by contract duration What the contractor planned to spend on the project up to a given point in time