Question: How is the current state value stream map different from a current state flow chart or process map? Question 2 options: It flows from left
How is the current state value stream map different from a current state flow chart or process map?
Question options:
It flows from left to right and top down.
There is no difference.
It includes process or waiting time estimates.
It uses sticky notes.
Step by Step Solution
There are 3 Steps involved in it