Question: How is the variance for a project found? Multiple choice question. By summing the variances of all the activities in the project. Using the formula
How is the variance for a project found? Multiple choice question. By summing the variances of all the activities in the project. Using the formula (ba6)2 . By summing the variance along the critical path. It is estimated based on the length of the project