Question: How is the variance for a project found? Multiple choice question. Using the formula ( b a 6 ) 2 . By summing the variance

How is the variance for a project found?
Multiple choice question.
Using the formula (ba6)2
.
By summing the variance along the critical path.
It is estimated based on the length of the project.
By summing the variances of all the activities in the project.