Question: How layout design differ for service organisation as compared to manufacturing organisation. Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellence assembly-
How layout design differ for service organisation as compared to manufacturing organisation. Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellence assembly- line balancing. She has been told that the firm needs to complete 96 instruments per 24- hour days. The assembly- line activities are:
| Task | Time (min) | Predecessors |
| A | 3 | - |
| B | 6 | - |
| C | 7 | A |
| D | 5 | A,B |
| E | 2 | B |
| F | 4 | C |
| G | 5 | F |
| H | 7 | D,E |
| I | 1 | H |
| J | 6 | E |
| K | 4 | G,I,J |
|
| 50 |
|
- Draw the precedence diagram
- If the daily (24 hour) production rate is 96 units, what is the highest allowable cycle time?
- If the cycle time after allowances is given as 10 minutes, what is the daily (24 hour) production rate?
- With a 10- minute cycle time, what is the theoretical minimum number of stations with which the line can be balanced?
- With a 10- minute cycle time and six workstations, what is the efficiency?
- What is the total idle time per cycle with a 10-minute cycle time and six workstations?
What is the best work station assignment you can make without exceeding a 10- minute cycle time and what is the efficiency?