Question: How many C's are required to make one A? Level Item Qty. 0 A 1 -1 B 2 --2 C 3 ---3 D 2 -1
How many C's are required to make one A?
| Level | Item | Qty. |
| 0 | A | 1 |
| -1 | B | 2 |
| --2 | C | 3 |
| ---3 | D | 2 |
| -1 | E | 1 |
| --2 | F | 4 |
| ---3 | G | 1 |
3
4
5
6
Which of the following are components of item C?
| Level | Item | Qty. |
| 0 | A | 1 |
| -1 | B | 2 |
| --2 | C | 3 |
| ---3 | D | 2 |
| -1 | E | 1 |
| --2 | F | 4 |
| ---3 | G | 1 |
answer choices
1. D
2. E, F, and G
3.E
4.G
Complete the following MRP Tableau for Item X.
Lot Size = MIN 50 Lead Time = 2
|
| 1 | 2 | 3 | 4 | 5 |
| Gross Requirements | 80 | 30 | 50 | 50 | 60 |
| Scheduled Receipts |
| 50 |
|
|
|
| Projected on Hand 100 |
|
|
|
|
|
| Net Requirements |
|
|
|
|
|
| Planned Order Receipts |
|
|
|
|
|
| Planned Order Release |
|
|
|
|
|
When should orders be placed for item X?
Group of answer choices
Periods 1, 2 and 3
Periods 2 and 4
Period 4
Periods 4 and 5
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts