Question: how many days: 1 PCP DATA COLLECTION AND VALIDATION PROJECT Duration Predecessor 2 1 . INFRASTRUCTURE 3 1 . 1 Confirm infrastructure requirements 5 days

how many days: 1 PCP DATA COLLECTION AND VALIDATION PROJECT Duration Predecessor
21. INFRASTRUCTURE
31.1 Confirm infrastructure requirements 5 days
41.2 Confirm infrastructure availability 5 days 3
51.3 Set up logins and passwords 3 days 4
61.4 Test logins and passwords 2 days 5
72 DATA COLLECTION AND VALIDATION MODULES
82.1 Confirm requirements and process flow 3 days 3SS
92.2 File pickup module
102.2.1 create folders for errors and validation records 2 days 8
112.2.2 develop batch header test code 3 days 10
122.2.3 develop error log 1 day 11
132.2.4 create emails 2 days 12
142.2.5 system test 5 days 13
152.2.6 release to test 0 days 14
162.3 File validation module
172.3.1 create folders for errors and desktop validation 3 days 8
182.3.2 develop field data format base 3 days 17
192.3.3 develop code to test data against field data format base 3 days 18
202.3.4 develop code for data progression to desktop validation
folder 4 days 19
212.3.5 develop code for rejection actions 5 days 20
222.3.6 create error logs, errors and confirmation emails 3 days 21
232.3.7 system test 6 days 22
242.3.8 release to test 0 days 23
252.4 Desktop validation
262.4.1 create folders for errors and upload to BiiP records 3 days 8
272.4.2 develop desktop review module
282.4.2.1 develop screens for view of data 4 days 8FS+1 day
292.4.2.2 develop screens for view of attachments 6 days 28SS
302.4.2.3 develop code to upload data for desktop validation 3 days 29SS
312.4.5 develop code to upload accepted data to BiiP 4 days 28;29;30
322.4.6 develop code to send rejected data to error folder 4 days 31SS
332.4.7 create error logs, errors and confirmation emails 3 days 32
342.4.8 system test 10 days 31;32;33
352.4.9 Release to test 0 days 34
362.5 Data upload to BiiP
372.5.1 create folders for errors and confirmations 3 days 8
382.5.2 develop integration code to upload data to BiiP 3 days 37
392.5.3 develop code to flag failed uploaded data 2 days 38
402.5.4 develop code to send failed data to error folder 3 days 39
412.5.5 create error logs, errors and confirmation emails 5 days 40
422.5.6 system test 10 days 41
432.5.7 released to test 0 days 42
442.6 Integration
452.6.1 develop integration code for module 14 days 14
462.6.2 develop integration code for module 24 days 23
472.6.3 develop integration code for module 34 days 34
482.6.4 develop integration code for module 44 days 42
492.6.5 system test 8 days 14;23;34;42;
45;46;47;48
502.6.6 released to test 0 days 49
512.7 Development complete 0 days 15;24;35;43;
50
523 TESTING
533.1 Test Centre setup 2 days 8
543.2 Onboard external test contractors 2 days 53
553.3 Develop test scripts 20 days 54
563.4 Develop test data 15 days 55
573.5 Acceptance Testing
583.5.1 test File pickup module 10 days 15
593.5.2 test file validation module 10 days 24
603.5.3 test desktop validation module 10 days 35
613.5.4 test data upload module 10 days 43
623.5.5 test integration 10 days 50
633.5.6 prepare final test reports 2 days 62
643.6 User Acceptance Testing
653.6.1 user training 1 day 62
663.6.2 user test file pickup module 5 days 65
673.6.3 user test file validation module 5 days 66
683.6.4 user test desktop validation module 5 days 67
693.6.5 user test data upload module 5 days 68
703.6.6 prepare final user test reports 2 days 69
713.7 Live data testing
723.7.1 acceptance test end to end using live data 3 days 58;59;60;61;
62
733.7.2 user test end to end using live data 3 days 2;66;67;68;
69;70
743.7.3 prepare final test reports 2 days 63;70
753.7.4 prepare acceptance reports 2 days 74
763.8 Testing complete 0 days 75
774 RELEASE TO PRODUCTION
784.1 Release plan
794.1.1 final documentation for support team 3 days 51;76
804.1.2 final documentation for user training 3 days 76
814.1.3 Change Control Board 1 day 79;80
824.1.4 Schedule release 2 days 81
834.1.5 Release to production. 1 day 82
84 Project completed 0 days 83
855 PROJECT MANAGEMENT

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!