Question: How many paths are in this network diagram? A(2) C(3) E(2) B(1) D(4) 02 3 Copy 05 A project has four activities - A, B,

How many paths are in this network diagram? A(2)
How many paths are in this network diagram? A(2)
How many paths are in this network diagram? A(2) C(3) E(2) B(1) D(4) 02 3 Copy 05 A project has four activities - A, B, C and D. - that take 4.3, 6 and 7 days, respectively. Activities A and B can start immediately. Activity C requires the completion of both A and B, and activity D requires the completion of activity C What is the total completion time for the project? 3 days 17 days 20 days Cannot be tell, not enough information provided

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!