Question: How many paths does the project have? 2 3 4 5 QUESTION 10 Chapter 17 , problem 7. What is the probability that the project

 How many paths does the project have? 2 3 4 5

How many paths does the project have? 2 3 4 5 QUESTION 10 Chapter 17 , problem 7. What is the probability that the project can be completed in 23 days or less? 0.35570.67360.85680.9686 QUESTION 11 Chapter 17, problem 7. Suppose it is now the end of the seventh day and that activities A and B have been completed, while activity D is 50 percent completed. Time estimates for the completion of activity D are 5,6 , and 7 . Activities C and H are ready to begin. What is the probability of finishing the project by day 23 ? 0.6433 0.3129 0.0582 0.0186