Question: How many paths does the project have? 2 3 4 5 What is the probability that the project can be completed in 23 days or

How many paths does the project have?

2

3

4

5

What is the probability that the project can be completed in 23 days or less?

0.3557

0.6736

0.8568

0.9686

How many paths does the project have? 2 3 4 5

TIME IN DAYS \begin{tabular}{ccccc} \cline { 3 - 5 } Activity & Immediate Predecessor & Optimistic & Most Likely & Pessimistic \\ \hline A & & 5 & 6 & 7 \\ B & & 8 & 8 & 11 \\ C & A & 6 & 8 & 11 \\ D & & 9 & 12 & 15 \\ E & C & 5 & 6 & 9 \\ F & D & 5 & 6 & 7 \\ G & F & 2 & 3 & 7 \\ H & B & 4 & 4 & 5 \\ I & H & 5 & 7 & 8 \\ End & E, G, I & & & \end{tabular}