Question: How many statements are corrects? Schedule the progress on the three Jobs A,B,C, using a Gantt chart. Scheduled time is ***. Completed time is 'X'.
How many statements are corrects?
Schedule the progress on the three Jobs A,B,C, using a Gantt chart. Scheduled time is ***. Completed time is 'X'. Queue time is - Gantt Chart Day Beginning Ending Work Day 1 2 3 4 5 6 7 8 Day Completed Job A 1 5 4 X X X X Job B 2 6 - X X Job C 3 8 * * * . . XXX Question 11. Consider the jobs to be scheduled on two servers. Jobs ABCDE Processing Time Work Center 1 8 6 11 5 12 Processing Time Work Center 2 3 14 4 13 7 Based on the Johnson's Rule schedule, how many statements are correct? 0 1 2 3 (A) The total processing time of the schedule is 46 (B) The total idle time of work center 1 is 0 (C) The total flow time of Job A is 46