Question: + how many units can be produced per week ( assuming 8 hours of work/day and 5 working days per week) A continuous stop watch

+ how many units can be produced per week ( assuming 8 hours of work/day and 5 working days per week)
A continuous stop watch time study was conducted on an operation that consists of 5 elements as shown in the table below: -Elements 1 2 2 3 4 5 Ratings Load machine 0.1573 1.477 21795 40115 5.438 127 Run 0.7974 2.117 3.436 4.755 0.675 100 (Automatic) Unload 1.092 2.409 3.717 5.043 61367 130 machine Inspect 1.323 2.64 3.956 5.270 6.50 105 Material 6.88 95 handling Note: All measurement units are in term of minutes. Selected Time Normal Time Allowances ko) Tsell Tnor VE A1 Tsel2= Thor 2- A2= n Tsel3= Tno 3 ACE a Tsel4= nor- A4- Tse15 Tnor 5 A5- 01- Assuming 39 personal allowances and 3% fatigue allowances and 2 % Delay allowances find the standard time to produce one unit? Standard time element 1) = minutes Standard time (element 2= minutes Standard time (element 3) minutesStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts