Question: How much additional cost is needed to crash the project by one day? Construction of a building is based on the following CPM network: Predecessor

How much additional cost is needed to crash the

How much additional cost is needed to crash the project by one day?

Construction of a building is based on the following CPM network: Predecessor Activity A B C Normal Time 6 8 2 Successor B, C, D E F F, G G G A B, A A B C, D OO | Ouu WN OOO Normal Cost $ 100 80 40 80 80 60 120 Crash Time 2 2 1 2 3 1 2 Crash Cost $ 150 140 60 120 140 100 160 E F G E, F, D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!