Problem LO Construction of a building is
Construction of a building is based on the following CPM network:
Activity Predecessor Successor Normal
Time Normal
Cost Crash
Time Crash
Cost
A B C D $ $
B A E
C B A F
D A F G
E B G
F C D G
G E F D
Draw the network and answer the following questions.
a What are the normal project completion time and normal cost?
b Identify the critical path. You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.
multiple choice
ADFG
ABEG
ABCFG
ADG
ACFG
c How much additional cost is needed to crash the project by one day?
This can be accomplished most effectively by crashing any one of which three activities below? You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.
check all that apply
Aunanswered
Bunanswered
Cunanswered
Dunanswered
Eunanswered
Funanswered
Gunanswered
d What is the minimum time for project completion?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock