Question: How much would it cost to crash the time a) by 1 day b) by 2 days c) by 3 days d) by the maximum

How much would it cost to crash the time a) by 1

How much would it cost to crash the time

a) by 1 day

b) by 2 days

c) by 3 days

d) by the maximum you can possibly crash

e) graph Time vs. Cost for this project

Activity A E I K M N O SUW Predecessor K O W TU U A E, I, M J DIS U Regular Time when Time (d) fully crashed (d) Cost ($) 1 1 500 1 700 200 250 600 500 3 2 4 5 3 8 1 3 15 6 1 2 3 2 6 1 2 13 3 200 900 100 1000 200 Regular Cost when fully crashed ($) - 900 300 400 700 1000 2000 500 5000 800