Question: For the following project Activity Predecessor Regular Time (d) Time when fully crashed (d) Regular Cost ($) Cost when fully crashed ($) A K 1
For the following project
| Activity | Predecessor | Regular Time (d) | Time when fully crashed (d) | Regular Cost ($) | Cost when fully crashed ($) |
| A | K | 1 | 1 | 500 | - |
| E | O | 3 | 1 | 700 | 900 |
| I | W | 2 | 1 | 200 | 300 |
| J | U | 4 | 2 | 250 | 400 |
| K | U | 5 | 3 | 600 | 700 |
| M | A | 3 | 2 | 500 | 1000 |
| N | E,I,M | 8 | 6 | 200 | 2000 |
| O | J | 1 | 1 | 900 | - |
| S | U | 3 | 2 | 100 | 500 |
| U | - | 15 | 13 | 1000 | 5000 |
| W | S | 6 | 3 | 200 | 800 |
How much would it cost to crash the time
a) by 1 day?
b) by 2 days?
c) by 3 days?
d) by the maximum you can possibly crash?