Question: How should the lessons learned from a project be communicated? a . ) By distributing the lessons learned via company - wide email without prior
How should the lessons learned from a project be communicated?
a
By distributing the lessons learned via companywide email without prior reviews
b
By keeping the lessons learned confidential and only sharing them with the project sponsor
c
By sharing the lessons learned with project stakeholders through a meeting, if possible
d
By posting the lessons learned document on the company bulletin board for public access