Question: how to do ? Construct AON & AOA network. Find the critical path. Activity Immediate Duration in seconds Predecessor Take jack and tool from boot
how to do ?

Construct AON & AOA network. Find the critical path. Activity Immediate Duration in seconds Predecessor Take jack and tool from boot N/A 30 B Remove hub cap 25 C Loosen wheel nuts B 45 D Place jack under car A 25 E Lift car C, D 30 F Remove spare wheel from boot None 20 G Remove wheel nuts and wheel E 25 H Place spare wheels on the studs GF 10 I Screw nuts half tight on studs H 20 J Lower car and remove jack I 25 K Replace jack on boot J 10 L Tighten nuts on studs J 15 Place punctured wheel and tools in boot L 30 N Replace hub cap L 10