Question: how to do ? please show the step, thanks Consider the following project (times given in days). Find: Predecessors Activity 8 b a 1. The
how to do ? please show the step, thanks

Consider the following project (times given in days). Find: Predecessors Activity 8 b a 1. The network. 2. All expected activity times, variances, and slacks. 3. The critical path and expected completion time. 4. The probability the project will be done in 23 days. 5. The completion time corresponding to 95% probability. 2 2 2 3 3 4 4 6 0 1 36 d b 7 2 8 5 8 6 9 e a c.b c.b de
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock