Question: Question 3 7 pts Duration Activity Predecessor (weeks) none 6 a b none 9 a, b 3 d ce 7 e b 2 f e

Question 3 7 pts Duration Activity Predecessor
Question 3 7 pts Duration Activity Predecessor (weeks) none 6 a b none 9 a, b 3 d ce 7 e b 2 f e 000 8 h 5 f.g In order to manufacture tables faster to meet market demand you are in charge of redesigning and implementing a new manufacturing process. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. Which activity has the MOST slack time? F D