Q2. . (a) Explain the following terms used in project management: (i) Earliest event time Latest event times (iii) Critical path method or analysis (b) Figure Q3 shows a typical project schedule. Insert the earliest event and latest event times. (i) Draw the critical path table. (ii) Determine the total project time. (111) The critical path. D H A 3 2 B 4 6 F 5 Figure Q3