Question: how to draw a gantt chart? ACTIVITY Type 1 Resource Required TYPE 2Resource Required Predecessor Optimistic Most Probable Pessimistic A 3 0 - 4 5
how to draw a gantt chart?
| ACTIVITY | Type 1 Resource Required | TYPE 2Resource Required | Predecessor | Optimistic | Most Probable | Pessimistic |
| A | 3 | 0 | - | 4 | 5 | 6 |
| B | 5 | 4 | - | 8 | 9 | 10 |
| C | 4 | 1 | A | 7 | 7.5 | 11 |
| D | 2 | 0 | B | 7 | 9 | 10 |
| E | 4 | 3 | B | 5.5 | 7 | 9.5 |
| F | 2 | 7 | D | 5 | 6 | 7 |
| G | 6 | 2 | E | 6 | 7 | 8 |