Question: How to solve 4 G Il . elearning.ju . edu.jo task, prone to a lot of errors. At this point, the need for a specific
How to solve
G Il
elearning.juedu.jo
task, prone to a lot of errors. At this point, the need for a specific algorithm for crashing a schedule is needed, as well as a preliminary programmed sample.
Analysis And Algorithm
The Traditional Crashing Method
The most basic and correct crashing method is the manual method, where activities are crashed on a daybyday basis. This method, although resulting in correct results, is very timeconsuming and can create an obstacle for project managers with limited time. The basic information needed to perform this method are five items, along with the project network diagram. First, the project manager needs to prepare a list of the activities, with the following attributes for each activity: normal cost, normal duration, crash cost, and crash duration. To determine the normal duration and the crashed duration, he must determine the budgeted quantity of work as well as the normal rate of productivity and the maximum rate of productivity. Then, he calculates the durations according to the following formulas and
Normal Duration
Crahsed Duration
Afterward, the slope is calculated, which is the daily increase in an activity cost. This slope is calculated using the formula:
Slope
Furthermore, when crashing the project, a new set of critical paths may emerge and the crashing procedure needs to take those new critical paths into consideration. On the other hand, when crashing an ongoing project schedule, the project manager will follow the same instructions discussed above, but with one major difference. An ongoing schedule has completion percentages for activities, and therefore the originally schedule durations should be replaced by remaining durations, and the crash duration shall be multiplied by the remaining percentage till completion, and rounded up The completion percentage shall be determined using formula after determining the actual quantity of work performed.
Completion Percentage
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
