Question: how to solve part A Q1. Given the product structure, master production schedule, and inventory status in the Figure below and assuming the requirements for

how to solve part A Q1. Given the product

how to solve part A

Q1. Given the product structure, master production schedule, and inventory status in the Figure below and assuming the requirements for each BOM item is 1 a) develop a gross requirements plan for Item C, b) develop a net requirement plan for Item C Master Production Schedule for X1 PERIOD 7 8 9 10 11 11 12 Subs X1 Gross requirements 50 20 100 LEAD TIME ON HAND LEAD TIME ON HAND ITEM ITEM E ca D X1 B1 B2 A1 1 2 2 1 50 20 20 5 D E 1 1 3 0 0 JO