Question: Redo Problem 9.27 with the following: center-to-center spacing of piles = 30 in., length of piles = 45 ft, D = 12 in., c u
Redo Problem 9.27 with the following: center-to-center spacing of piles = 30 in., length of piles = 45 ft, D = 12 in., cu = 860 lb/ft2, and FS = 3. Use Table 9.10.
Reference: 1
The plan of a group pile is shown in Figure P 9.27. Assume that the piles are embedded in a saturated homogeneous clay having a cu = 90 kN/m2. Given: diameter of piles (D) = 316 mm, center-to-center spacing of piles = 600 mm, and length of piles = 20 m. Find the allowable load-carrying capacity of the pile group. Use Table 9.10 and FS = 3.
Reference:
Reference: 2
Step by Step Solution
3.40 Rating (153 Votes )
There are 3 Steps involved in it