Question: ( i ) ( 4 0 points ) Determine the project s SPI, and CPI at this point ( end of day 4 8 )
i points Determine the projects SPI, and CPI at this point end of day ii points Interpret the SPI and CPI by stating and explaining whether the project is doing betterworse than plan on schedule and cost. Also, forecast the actual cost at completion of Activity assuming that its future expenditure past day is reflective of the past expenditure pattern Activity # Duration days Predecessors Budget Actual Cost Complete NA $ $ $ $ $ $
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
