Question: I already submitted this question with different numbers and it was all wrong, so please make sure they are right and how to do them
I already submitted this question with different numbers and it was all wrong, so please make sure they are right and how to do them with calcuations
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
ActivityTime (weeks)Immediate Predecessor(s)ActivityTime (weeks)Immediate Predecessor(s) A7-E4B B7-F6B C3AG11C, E D3AH7D , F