I am astounded that we cannot find the cost records for the month of July 2021 said
Question:
I am astounded that we cannot find the cost records for the month of July 2021” said Greg Andrews, plant manager of Detroit Component Works (DCW). “ I have a division meeting to attend where I will be asked about the plant’s July performance compared to June. All I have now are the weighted average cost figures, but those numbers are hardly helpful in answering the question of whether we have improved the efficiency of our performance this month compared to the previous months. I think we have improved the efficiency of our operations. so I was expecting to report some good news at the division meeting. I need those July numbers now.” DCW makes complex aircraft engine components in one operation which combines —machining and assembly. After the units are completed they are transferred to cost of goods sold.
The below is a summary of the Assembly operations in July of 2021.
Physical Direct Conversion
Units Materials Cost
W-in-P, 7/1* 120 $15,000 $8,325
Cost Added
during July 200
Completed
during July 220
W-in-P, 7/31** 100
Cost Added
during July ? ?
Weighted average cost
Per equivalent unit $131.25 $114
* Degree of Completion: Direct Materials, 100%; Conversion Cost, 62.5%
**Degree of Completion: Direct Materials, 100%, Conversion Cost, 80%.
Instructions:
For each cost element (Direct Materials and Conversion Cost) compute the unit cost for work that was done on the 7/1 units prior to 7/1.
For each cost element (Direct Materials and Conversion Cost), compute the equivalent units of work done in the current period only. (FIFO).
Calculate the Assembly Department costs to account for in July 2021 for each cost element. (Direct Materials and Conversion Cost) (You will need to use the weighted average method to determine this.)