Question: I am having difficulty with this assignment: Vicki needs to make 240 pizzas in the 4 hours of the peak demand period in the evening

I am having difficulty with this assignment:

I am having difficulty with this assignment:I am having difficulty with this assignment:

Vicki needs to make 240 pizzas in the 4 hours of the peak demand period in the evening and wants to have an assembly line balanced for this with the data below: Example 10.4 Vicki's Pizzeria and the Precedence Diagram | Immediate | Task Time Work Element Task Description Predecessor (seconds Roll dough None 50 B Place on cardboard backing A C Sprinkle cheese B 125 D Spread Sauce C 15 E Add pepperoni D 12 F Add sausage Add mushrooms 15 Shrinkwrap pizza E.F.G 18 Pack in box 15 Total task time 165 D 10 (12 sec) (50 sec) (5 sec) (25 sec) (15 soc) (10 sec) (18 sec) (15 ) (15 C) 1) What is the Cycle time? 2) What is the minimum number of workstations required? 3) Conduct the assignment of the tasks to workstations using the Longest Task Time heuristic: Workstation Task Ready Task Assigned Task Time Idle Time 4) What is the efficiency of this assembly line

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!