QUESTION 1
-
The responsiblity assignment matrix (RAM) illustrates who will be responsible for the work.
True
False
QUESTION 3
-
Which of the following is not a way to reduce durations of activities
Increase activities speed through improved methods or technology
Remove slack
Reduce the scope of the activity
Apply more resources
QUESTION 9
-
The work package is the lowest level work item of any one branch in the WBS.
True
False
QUESTION 10
-
An activity cannot start until all of the preceding activities that are linked to it by arrows are:
Finished
Defined
Staffed
Properly assigned costs