Question: I. Create Project 1 . Create a blank project. 2 . Open the Project Information dialog box and enter the start date as today s
I. Create Project
Create a blank project.
Open the Project Information dialog box and enter the start date as todays date.
Enter Gwendolyns Gourmet Cookbook as the title by selecting Advanced Properties from the
Project Information section from the Info section of the File tab.
II Enter Tasks
Click VIEWGANTT CHART TOOLS and enter the following tasks:
Acquisition
Receive manuscript
Edit Content
Handoff to Editorial
Editorial
Organize manuscript for copyedit
Copyedit
Incorporate copyedits
Handoff to Production
Design and Production
Design cover
Set pages
Design interior illustrations
Pages Review
Proofread and index
Incorporate first pages review
Send proofed pages to Production
Enter page corrections and index
Color prep and printing
Send to color house
Generate proofs
Print and ship
Type the name of each item into the Task Name column of the Entry table, beginning with the first row.
Note: the underscore represents major tasks in the outline.
Save your file by selecting File, Save As Name your project, YourLastNameCookbook
Click Project Summary Task and Summary Tasks from the FORMAT tab under GANTT CHART TOOLS.
Gwendolyns Gourmet Cookbook should appear in Line
This project has five summary tasks: Acquisition, Editorial, Design and Production, Pages Review and
Color prep and printing. Click on Receive manuscript under Acquisition and drag the mouse through the
cells to Handoff to Editorial. Click the Indent task button on the Ribbon under the Schedule group of the
Task tab. Do the same for the tasks under Editorial, Design and Production, Pages Review and Color prep
and printing.
III. Enter Task Durations
Enter the following durations for each task:
Children's Gourmet Cookbook Duration
Acquisition
Receive manuscript days
Edit content days
Handoff to Editorial days
Editorial
Organize manuscript for copyedit days
Copyedit days
Incorporate copyedit changes days
Handoff to Production days
Design and Production
Design cover days
Set pages days
Design interior illustrations days
Pages review
Proofread and index days
Incorporate st Pages review days
Send proofed pages to Production days
Enter page corrections and index days
Color prep and printing
Send to color house day
Generate proofs days
Print and ship days
The tasks with a duration of days are milestones.
Make all tasks Automatically scheduled tasks by clicking the Task Name column heading then the
Auto Schedule button under the Task tab, Tasks group. If changes are made, you may need to repeat
this step to reset all the automatically scheduled times.
IV Enter task dependencies
Establish the following task dependencies:
Children's Gourmet Cookbook Predecessors
Acquisition
Receive manuscript
Edit content Receive manuscript
Handoff to Editorial Edit Content
Editorial Acquisition
Organize manuscript for copyedit
Copyedit Organize manuscript for copyedit
Incorporate copyedit changes Copyedit
Handoff to Production Incorporate copyedit changes
Design and Production
Design cover
Set pages Design cover
Design interior illustrations
Pages review Design and Production, Editorial
Proofread and index
Incorporate st Pages review Proofread and index
Send proofed pages to Production Incorporate First Pages review
Enter page corrections and index Send proofed pages to Production
Color prep and printing Pages review
Send to color house
Generate proofs Send to color house
Print and ship
Click on the task that will be the predecessor Receive manuscript hold the CTRL key down then click on
the task that it precedes Edit content In the Task tab, click the Link Tasks button under the Schedule
group. If the tasks are one right after another hold the mouse down and drag until all tasks are selection.
Type in the dependency numbers when there are more than one dependency.
Several tasks require restrictive dependencies. For example
Task New Restrictive Predecessor
Design and Production Editorial Start to Start
Design interior illustrations Set pages Start to Start
Print and ship Generate proofs finish to start plus days
Doubleclick the Task Name for the first task, Design and Production, as shown above. Click the
Predecessors tab in the Task Information dialog box. Click in the Task Name column and select Editorial
from the Drop Down list. Click the cell under Type and select StarttoStart from the dropdown list. Do
the same for the second task, Design interior illustrations. For the third task, Print and ship, doubleclick
the Task Name, click on the Predecessors tab, click in the Task Name column and select Generate Proofs
from the Drop Down list. Click the cell under Type and select FinishtoStart from the dropdown list.
Click the cell under Lag and select from the
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock