Question: I don't understand how to work this problem completely. Aggregator Industries does cement pouring jobs for homes and businesses. Below is information related to its
I don't understand how to work this problem completely.
Aggregator Industries does cement pouring jobs for homes and businesses. Below is information related to its Overhead application:
Estimated Overhead Cost$ 240,000Estimated Direct Labor Hours29,000Actual Direct Labor Hours31,587Estimated Machine Hours74,000Actual Machine Hours68,541Depreciation of Mixing Equipment$ 48,000Depreciation of Pouring Equipment$ 52,000Fuel for Cement Truck$ 3,900Supervisor Salaries$ 104,000Advertising Expense$ 2,850Rent Expense for Cement Yard$ 23,000Required:
- Determine the Predetermined Overhead Rate if the Cost Driver is Direct Labor Hours.
- Calculate the Over/Underapplied Overhead.
- Create a journal entry to dispose of the Over/Underapplied Overhead.
- Repeat steps 1-3, but with Machine Hours as the Cost Driver.