Question: I don't understand these two questions. Please help me. 1. As you develop a master production schedule, a customer calls you and informed you that
1. As you develop a master production schedule, a customer calls you and informed you that due to changes to market condition, they will need to increase their order from you. Which part of your MPS is most likely going to be DIRECTLY affected?
A. Scheduled receipts
B. Gross requirements
C. Available inventory
D. Net requirements
2. One of the components necessary for your product is cheap and usually sourced from overseas. Because of international shipping and customs clearance, your company would rather prefer to not order it on an as needed basis. Which of the following approaches should you use to manage this component's inventory and orders?
A. Lot for lot
B. Fixed order quantity
C. Period order quantity
D. Reverse auctions