Question: 1. As you develop a master production schedule, a customer calls you and informed you that due to changes to market condition, they will need
1. As you develop a master production schedule, a customer calls you and informed you that due to changes to market condition, they will need to increase their order from you. Which part of your MPS is most likely going to be DIRECTLY affected?
A. Scheduled receipts
B. Available inventory
Please choose one of these two answers