Question: ( i ) For a drill press operation, the following data are known: - - - - - - - - - - - -

(i) For a drill press operation, the following data are known:
---------------------------------------------------------------------------------------------------
Work Elements Observed time Rating
(min./pc.)%
---------------------------------------------------------------------------------------------------
1. Load drill press 0.20115
2. Drill hole with automatic power feed0.25100
3. Check tolerance of the last piece produced0.10110
during machine cycle (#2) with go/no-go gauge
4.Unload drill press0.15120
----------------------------------------------------------------------------------------------------
The company allows: 5% for personal, 5% for unavoidable delays and 5% for fatigue.
Calculate the normal time and the standard time for the operation in min/pc.
(ii) Why is it important to maintain time standards properly/accurately, especially for the company which follows a wage incentive program? What procedure would you recommend for a sound program for the maintenance of time standards?
(iii) Show by means of a typical productivity increase graph or learning, the most desirable stage in the production to establish the time standard.
( i ) For a drill press operation, the following

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!