Question: (i) For the project details shown below, draw the AON network diagram and determine the following for all activities: (a) early start, (b) early finish,


(i) For the project details shown below, draw the AON network diagram and determine the following for all activities: (a) early start, (b) early finish, (c) late start, (d) late finish, (e) total float, and (f) free float. Assume Finish to Start (FS) precedence relationships. Deterministic Immediate Free Critical/ Activity Duration Predecessor(s) Early Early Late Late Float Total Non- Start Start float (days) Finish Finish critical P 15 Q 15 P 25 P, Q 10 20 Q,C 15 E 15 F H 20 10 D,F 3 15 DJ
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
