Question: I had raised this questions before and was given calculation that has activity E with slack time but it was not considered in critical path.

I had raised this questions before and was given calculation that has activity E with slack time but it was not considered in critical path. Can someone please help me with problem?
Chandak Condominium, located on the Kolshet, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times. 1. Draw a project network. 2. What are the critical activities? 3. What activity has the most slack time? 4. Will the project be completed by September 1
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
