Question: I have 10 mins please answer as soon as u can! Thank you QUESTION 1 Table 10.8 Suppose that the following six jobs must be

I have 10 mins please answer as soon as u can! Thank you

I have 10 mins please answer as soon as u can!

QUESTION 1 Table 10.8 Suppose that the following six jobs must be scheduled through a computer repair facility (repair times are shown in days): Customer A B Time Since Order Arrived (days ago) 10 7 Repair Time 5 3 Due Date (days from now) 11 9 D 5 5 7 8 10 8 7 6 E F 6 8 4 6 Use the information in Table 10.8 to answer this question. Which customer's computer is repaired the latest (the most past due) if an EDD sequence is obeyed? O Customer F O Customer E O Customer B O Customer A