Question: I have a process making pizzas. Task Predecessor Time (Seconds) A None 45 B None 30 C A, B 45 D B 20 E C

I have a process making pizzas. Task Predecessor Time (Seconds) A None 45 B None 30 C A, B 45 D B 20 E C 10 F D, E 27 G E 40 If my desired output rate is 75 pizzas per hour, what is the efficiency of my setup? (Answer in the nearest percentage.) *please show work* *The answer is 71 +-2%, but I need to know how to show the work for that answer^