Question: I have a process making pizzas. Task Predecessor Time (Seconds) A None 45 B None 30 C A, B 45 D B 20 E C

I have a process making pizzas.

Task Predecessor Time (Seconds)
A None 45
B None 30
C A, B 45
D B 20
E C 10
F D, E 27
G E 40

If my desired output rate is 75 pizzas per hour, what is the efficiency of my setup? (Answer in the nearest percentage.) *please show work*