Question: I have the answer, but can someone explain 3b) for me please, I don't know how the tasks and the Idle Time come out, I

 I have the answer, but can someone explain 3b) for me please, I don't know how the tasks and the Idle Time come I have the answer, but can someone explain 3b) for me please, I don't know how the tasks and the Idle Time come out, I will give a thumbs up.

3. Consider the assembly line balancing problem represented by the network in the figure below. The performance times are shown above the nodes. (a) Determine positional weights for each of the activities. (b) For a cycle time of 15 units, find the balance obtained using the ranked positional weight technique. N=T/C=68/15=4.53=5